O2521-01 Interior Remodel - St. Louis County Regional State Office Building
The Work includes, but is not limited to, new metal stud framing, gypsum board, interior paint, doors and frames with sidelites, floor and wall tile, carpeting, epoxy flooring, acoustic ceiling tiles and suspension system, toilet accessories, custom millwork, solid surface and quartz countertops, systems furniture, and various office furniture. Work also includes HVAC system modifications, water closets, sinks, lighting, data, and electrical receptacles. The Work is to be substantially complete in 5 phases. Refer to Floorplans for phasing locations. Phase 1 – Floor 1 – Substantially complete by April 15, 2025; Phase 2 – Floor 2 – Substantially complete by May 1, 2025; Phase 3 – Floor 1 – Substantially complete by May 15, 2025; Phase 4 – Floor 4 – Substantially complete by June 1, 2025; and Phase 5 – Floor 5 - Substantially complete by July 1, 2025.
Issued for Bid